Works of Khan Sheikhoun-Maarat al-Nu’man power link completed

Idleb, SANA- Idleb Electricity Company’s technical workshops completed on Saturday works of electricity link project between Maarat al-Nu’man and Khan Sheikhoun cities in Idleb liberated countryside.

Director of the Electricity Company Mamdouh Abdo told SANA in a statement that the works of the electricity link extended with a length of 28 kilometers, including installation of two low-voltage transformers to supply the houses and commercial markets with electricity.

Abdo pointed out that it is expected that all works of the project to be completed by mid of current month, with a total cost of SYP 3 billion.

Hala Zain

Check Also

Mikdad sends message of condolence to Bagheri on demise of Raisi and Abdollahian

Damascus, SANA- Foreign and Expatriates Minister Fayssal Mikdad sent a message of condolence to Ali …